Answer:
D. $8,780
Explanation:
the budgeted expected 16 days of activity for the Snow removal's. The Budgeted will reflect cost for this level of activity.
so we have a budgeted cost of:
430 dollar per day x 16 days of activity = 6,880 variable cost
+ fixed cost in the magnitude of         1,900 Â
 total budgeted for Snow removal      8,780
The actual cost will be calclate with the actual days of activity.