Answer:
total ending WIP value     39,334.20
transferred-out          432.078.00
Explanation:
Ending work in proces inventory
we multiply the equivalent units by the cost per equivlent unit
materials 2,200 x 15.26 Â = Â 33,572
converion  940  x  6.13  =   5,762.2
then, we add them to get thetotal value of the ending WIP
 total ending WIP value   39,334,2‬
for the transferred out, we add both equivalent cost as this are complete.
And multiply by the whole amount 20,200
trasnferred out: 20,200 x (15.26 + 6.13) = 432.078