Answer:
Instructions are listed below.
Explanation:
Giving the following information:
The standards for the railroad cars are as​ follows: Standard tons of direct material​ (steel) per car 22 Standard cost per ton of steel $16.00 During ​ March, the company produced 1,500 cars. Related production data for the month​ follows: Actual materials purchased and used​ (tons) 7,000 Actual direct materials total cost $118,000
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (33,000 - 7,000)*16= $416,000 unfavorable