Answer:
Explanation:
                          2016                  2017
Contract price          =   2300000              2300000
Cost to date            =   (2100000)             (2160000)
Further estimated Cost   =   (80000)                   0
Profit                  =   120000                 140000
Stage of completion     =  2100/2180 = 96.33%         100%
As at Profit and loss
Revenue   2300*96.33    =  2215596.33              2300000
Profit      120*96.33     =  -115596.3303              -140000
Cost of Sales            =   2100000                 2160000  Â
For the period profit and loss
Revenue                =   2215596              84404
Cost of sales            =   (2100000)              60000                Â
Profit                   =   115596                 24404