Respuesta :
Answer:
OMG
1. The estimated tender bid for the project is $96,000.
2. The estimated profit on the project is $42,000.
3. Managers at OMG use this information to compare the actual costs incurred with the estimated costs. Â This enables them to determine if they can still achieve the same level of estimated profit, control the project's costs, and to benchmark future projects.
Explanation:
a) Data and Calculations:
Markup of total professional (engineering and scientist) labor costs = 80%
Markup of other costs = 50%
Estimated direct costs:
Input Costs Civil engineers 150 hours  $25 000
Environmental scientists 100 hours      15 000
Support labour 120 hours              10 000
Total direct labor costs              $50,000
80% markup                        40,000
Total direct costs                   $90,000
Other costs:
Travel 1 000 km           $1 000
Computer time 80 hours    2 500
Photocopying, phone, fax     500
Total other costs         $4,000
50% markup              2,000     $6,000
Total bid costs                     $96,000
Estimated project profit:
80% markup on direct labor costs      40,000
50% markup on other costs            2,000
Total estimated project profit        $42,000